The second stage of #WierzejkiMeatPlant investment is already behind us
Data: 22 December 2021
At this stage we have completed:
Glycol installation for the fat-processing area:
- installation of welded steel pipelines (approx. 500 mb)
- installation of 7 glycol coolers (including one 60 kW cooler)
- installation of 7 control modules at the coolers
- installation of a pump module with 3 circulation pumps
- wykonanie izolacji PUR w płaszczu z blachy (cała instalacja zewnętrzna i wewnętrzna)
- installation of electrical wiring (approx. 3335 mb)
- installation of 2 control cabinets of our production
- update of the existing SCADA system
Ammonia plant:
- rozbudowa istniejącej maszynowni amoniakalnej o:
- compressor unit with cooling capacity of 1413 kW
- spray-evaporative condenser equipped with 3 axial fans and a water pump
- dry cooler with 211.8 kW cooling power
- ammonia pumps 2 pcs
- installation of support structure for ammonia pipelines and ammonia/glycol exchanger
- installation of ammonia pipelines welded on a support structure for supplying the ammonia/glycol exchanger (approx. 420mb)
- installation of ammonia/glycol exchanger with 1000 kW cooling capacity and weight of 1857 kg
- leakage and strength tests of the installation